BLESSING v. HAWAIIAN DREDGING CO.

February 6, 1948

BLESSING et al.
v.
HAWAIIAN DREDGING CO., Limited, et al.



The opinion of the court was delivered by: MCGUIRE

This is an action in the nature of contract predicated on the overtime and liquidated damage provisions of the Fair Labor Standards Act, 29 U.S.C.A. § 201 et seq.

The plaintiffs are individuals who were employed by the defendant corporations in construction work involving the dredging, extension, enlargement and improvement of harbor, and sea and land plane facilities etc., at Guam and Wake Island.

 The plaintiffs bring this action on their own behalf and that of other employees of the same corporations similarly situated.

 The defendants have filed a motion for summary judgment, and cite in support thereof Sec. 9 of Public Law 49, Eightieth Congress, the so-called Portal-to-Portal Act, approved May 14, 1947, 29 U.S.C.A. § 258, which provides as follows:

 The plaintiffs contend that the administrative ruling of the former Chief of the Bureau of Yards & Docks of the Navy Department is not such an administrative ruling as would bring it within the meaning of Sec. 9, and if it should be held that it is, then the section is unconstitutional because it is violative of the Fifth Amendment in that it deprives plaintiffs of their 'vested right' to overtime compensation and liquidated damages without due process of law.

 There is no merit in either of these contentions. It cannot be gainsaid that the Chief of the Bureau of Yards & Docks speaks for the Secretary of the Navy, when functioning in this capacity. Title 5 U.S.C.A. §§ 429, 430 -- ; secondly, the claim that the section thus construed is unconstitutional because it deprives plaintiffs of vested rights, is equally untenable. Norman v. Baltimore & O.R. Co., 294 U.S. 240, 55 S. Ct. 407, 79 L. Ed. 885, 94 A.L.R. 1352, and also generally: Seese v. Bethlehem Steel Co., D.C., 74 F.Supp. 412. Burfeind v. Eagle-Picher Co., D.C., 71 F.Supp. 929 and cases therein cited. See also: Boehle v. Electro Metallurgical Co., D.C., 72 F.Supp. 21. See also re Sec. 9; Semeria v. Gatto et al., Sup., 75 N.Y.S.2d 140, 142.

 This being the view I take of the matter, the other questions raised of necessity become moot. Counsel will prepare proper orders.

19480206

© 1992-2004 VersusLaw ...

Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.