Moore v. District of Columbia Department of Employment Services

District of Columbia Court of Appeals

December 31, 2002


Petition for Review of a Decision of the District of Columbia Department of Employment Services (Dir. Dkt. 00-55)

Before Wagner, Chief Judge, and Reid and Glickman, Associate Judges.

The opinion of the court was delivered by: Glickman, Associate Judge

Argued November 21, 2002

Jacqueline D. Moore asks us to review a decision by the Director of the Department of Employment Services dismissing her claim for workers' compensation benefits as time barred under procedural regulations that the Department promulgated in 1994. Finding that the Director erred in applying these regulations retroactively to a voluntary compensation agreement that the parties made in 1990, we set aside the Director's decision and remand the case for the Director to decide it in light of the regulations then in effect.

Moore was working for Sheraton Washington Hotel as a housekeeper when she sustained work-related injuries in January 1988. Taking advantage of informal claim resolution procedures offered by the Office of Workers' Compensation (OWC), Moore and Sheraton voluntarily agreed to settle Moore's timely-filed workers' compensation claim. Under their initial agreement, which was reflected in a Memorandum of Informal Conference issued by the OWC in December 1988, Sheraton paid Moore temporary total disability benefits through August of 1989. From then on, pursuant to a subsequent Memorandum of Informal Conference issued in March of 1990, Sheraton paid Moore temporary partial disability benefits. Three and a half years later, however, in August 1993, Sheraton unilaterally ceased making these payments, for reasons not set forth in the record. *fn1

Moore took no action to recover her benefits for six and a half years. Then, in February 2000, she requested a hearing before the Department of Employment Services to enforce the March 1990 OWC Memorandum of Informal Conference and to modify her compensation as appropriate. Moore contended that statutory time limits on enforcing or modifying compensation awards *fn2 did not bar her action because the March 1990 Memorandum was not a final compensation order. Sheraton had made compensation payments to her by voluntary agreement, Moore maintained, and no order finalizing an award of the temporary partial disability benefits envisioned in the March 1990 Memorandum had ever been entered. Absent such a final order, Moore argued, the statutory limitations period for seeking to enforce or modify a compensation award never began to run and so had not expired.

The Hearing Examiner and, on appeal, the Director, rejected Moore's argument and consequently concluded that her claim was time barred. In agreement with the Examiner, the Director reasoned that under the Department regulation governing the informal resolution of workers' compensation claims, see 7 DCMR § 219 (1994), the March 1990 Memorandum became a final award by operation of law when no party requested a formal hearing within thirty-four days after the Memorandum was issued. *fn3

Unfortunately, what all concerned overlooked, including the Director, was that the Department of Employment Services did not promulgate the regulation on which the Director relied until 1994. See 41 D.C. Reg. 3213, 3221 (June 3, 1994) (amending 7 DCMR Chapter 2, "Private Sector Workers' Compensation Program"). The Director erred in applying that regulation to a Memorandum of Informal Conference that was issued four years before the regulation took effect. This error was not immaterial, for prior to 1994, the Department's regulations did not state that a Memorandum of Informal Conference could become final as a matter of law. *fn4 We therefore cannot uphold the Director's decision; when, as in this instance, an administrative agency decision "is based upon a material misconception of the law, this court will reject it." Jerome Mgmt, Inc. v. District of Columbia Rental Hous. Comm'n, 682 A.2d 178, 182 (D.C. 1996). *fn5

In this court, Moore and Sheraton debate whether the Worker's Compensation Act and the implementing regulations in force in 1990 should be construed to require the same result that the Director reached under the 1994 regulations. As the question is an open one, and as we generally "defer to the agency's interpretation of the statute and regulations it administers unless its interpretation is unreasonable" or is contradicted by the specific language of the law or its legislative history, Cathedral Park Condo. Comm. v. District of Columbia Zoning Comm'n, 743 A.2d 1231, 1239 (D.C. 2000), we decline to parse the relevant provisions before the Director weighs in on them. Accord, Wahlne v. District of Columbia Dep't of Employment Servs., 704 A.2d 1196, 1199 (D.C. 1997) ("[O]rdinarily this court will not attempt to interpret the agency's statute until the agency itself has done so.") Instead, we set aside the decision of the Director holding that Moore's claim for compensation is time barred, and we remand the case to enable the Director to consider in the first instance the applicability of the law and regulations in effect during the relevant time period.

So ordered.