American Forest Resource Council v. Caswell

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA


June 30, 2009

AMERICAN FOREST RESOURCE COUNCIL, ET AL., PLAINTIFFS,
v.
JAMES CASWELL, DIRECTOR, BUREAU OF LAND MANAGEMENT, ET AL., DEFENDANTS.

The opinion of the court was delivered by: James Robertson United States District Judge

MEMORANDUM

Fifteen years ago, the American Forest Resource Council, a timber industry group, sued to challenge a Bureau of Land Management plan to manage a million acres of federal forests in the northwestern United States. AFRC's position was that the plan unlawfully limited the harvesting of timber contemplated by the Oregon California Railroad and Coos Bay Wagon Road Grant Lands Act, 43 U.S.C. § 1181a, enacted in 1937. After years of litigation, the parties signed a settlement agreement, one provision of which obligated the BLM to "revise the Resource Management Plans for its Coos Bay, Eugene, Lakeview, Medford, Roseburg and Salem Districts by December 31, 2008." Dkt. #82 ex. A § 3.5. The case was dismissed without prejudice, but, under the terms of the settlement, this court retained jurisdiction to consider any motion to enforce the agreement. Id. § 4.3.

In October 2008 AFRC filed a motion to enforce, asserting in relevant part that the BLM has breached the Agreement's implied covenant of good faith by promulgating the contemplated revised plan without initiating consultation with the U.S. Fish and Wildlife Service or the National Oceanic and Atmospheric Administration about the plan's impact on endangered or threatened species and their critical habitat. See, Section 7(a)(2) of the Endangered Species Act (ESA), 16 U.S.C. § 1536 (a)(2). Plaintiffs' theory is that this failure to consult will cause a federal court in the Ninth Circuit to enjoin the plan from taking effect, thereby depriving plaintiffs of the benefit of their bargain. The parties agree that Ninth Circuit litigation regarding the alleged failure to consult is inevitable and imminent: three challenges to the BLM plan had already been filed when the instant motion was argued.*fn1

Because there is no evidence of subjective bad faith, because the Agency's "no effect" determination is not facially invalid, and because any consulting duty may have been satisfied, plaintiff's theory of breach is too tenuous to support an enforcement order, especially when neither a direct challenge to the plan's validity nor the administrative record is before this court. Plaintiffs' motion must therefore be denied.

Analysis

Plaintiffs do not attempt to show that any of the recognized indicia of bad faith are present --- such as sharp dealings, a lack of diligence or slacking off, a desire to evade the spirit of the bargain, abuse of the power to specify terms, or acting in a way targeted to frustrate the other party's benefit or performance. See, North Star Alaska Housing Corp. v. U.S., 76 Fed.Cl. 158, 187-188 (Fed. Cl. 2007) (collecting cases); See generally, Restatement (Second) of Contracts § 205 (1981). Plaintiffs indeed concede that the defendants believe the revised plan will take effect and desire that it do so. Instead, plaintiffs argue, it is so likely that the plan will be enjoined by a court in the Ninth Circuit that their "reasonable expectations . . . regarding the fruits of the contract" have been destroyed. Centex Corp. v. U.S., 395 F.3d 1283, 1305 (C.A. Fed. 2005). The analogy offered at oral argument involved the construction of a house: the contract contains no provision obligating the contractor to obtain a building permit, and he does not, with the result that the owner cannot move into the house. The contractor (plaintiffs argue) has breached the covenant of good faith.

Even if those facts make out a breach of the covenant of good faith, the analogy is unconvincing. The contractor's omission was certain to prevent the house from being used.

Nothing is so certain here: the defendants have determined that the plan will have "no effect" on endangered or threatened species, Opp. at 13, and there is substantial Ninth Circuit authority that a "no effect" determination obviates the ESA's consultation requirement unless it is found to be an abuse of discretion. See, Defenders of Wildlife v. Flowers, 414 F.3d 1066, 1070-1071 (9th Cir. 2005); Southwest Center for Biological Diversity v. U.S. Forest Service, 100 F.3d 1443, 1447 (9th Cir. 1996); 51 Fed.Reg. 19926, 19949 (June 3, 1986) ("The Federal agency makes the final decision on whether consultation is required, and it likewise bears the risk of an erroneous decision."); 73 Fed. Reg. 76,272, 76,280-81 (Dec. 16, 2008) (to be codified at 50 C.F.R. § 402).

"[C[lear and convincing evidence" is necessary to show that the government did not act in good faith. Am-Pro Protective Agency, Inc. v. United States, 281 F.3d 1234, 1239-40 (Fed. Cir. 2002). Plaintiffs have not made such a showing. Defendants have adopted a course of performance that is not facially defective. A thorough analysis of that performance may establish that there was no duty to consult, or that any duty to consult has been satisfied,*fn2 or that defendants have failed in their duty. That analysis, however, is for the federal courts in the Ninth Circuit, and not for this court.*fn3

An appropriate order accompanies this memorandum.